Phase 3 Details

Phase 3 is a longterm goal and completes the project.  Priority #1 is a large building that serves as a team-house, staff apartments, and housing for Bible Institute residents. This phase also includes additional housing for mor missionary families. And finally, a covered 5v5 field giving more options for tournaments, leagues, camps, training, and multi-sports.

** Update **

During Phase 2 we adjusted some details for missionary housing. The general idea, number of family dwellings, and corresponding cost, stays the same. But we pushed 3 missionary homes into Phase 3 in order to prioritize getting a head start on the Team-House and Staff Housing. 

Click image to enlarge

Team-house, Staff & Bible Institute Resident Housing

One of our favorite buildings included in the plans.  Level 1 has 4 apartments for staff, Bible Institute residents, or missionaries/pastors in training... and level 2 is the team-house space.

The 4 apartments on level 1 each have a 2 private bedrooms, living room, kitchen, and back-patio laundry station.

The team-house space on the second floor has 3 large rooms, each able to sleep 10-12 people, and each equipped with private bathrooms and showers. The 4th room on the second floor is a large room with a kitchen and living space. 

There is also a spiral staircase going up to the rooftop terrace.

Original cost was 456,000, but we received a 93,000 head start in Phase 2 after the re-org of missionary housing.

Remaining Cost: $363,000

Basketball Court / Multi-purpose Area

In the plans, the basketball / multipurpose court is immediately outside the entrance into the Academy building. 


Cost: $47,300


5v5 Field

Update: We have eliminated the covered 5v5 field from construction plans, because of limited space due to where the water-well had to be built.

Cost: N/A

3 Missionary Homes

After making adjustments to the construction order, we included 2 Missionary Homes in Phase 2 (instead of 3) and we look to build 3 more Missionary Homes in Phase 3 (instead of 2).

Cost: $279,000 (93k each)



Total Cost for Phase 3: $689,000 

$688 has been given to date!

Current need: $688,312

Declare his glory among the nations, his marvelous works among all the peoples!  Psalm 96:3